复杂环境下立窑楼与窑体同时定向爆破拆除
SIMULTANEOUS DIRECTIONAL DEMOLITION BLASTING OF SHAFT KILN BUILDING AND KILN STRUCTURE UNDER COMPLEX SURROUNDING CONDITIONS

付武,王健,付博,马玉罄,毛广田
FU Wu1,WANG Jian1,FU Bo1,MA Yu-qing2,MAO Guang-tian3(1.65066 Troops

摘要(Abstract):

介绍了大连市鞍钢集团某水泥厂内立窑楼与立窑体建筑物的同时拆除的爆破设计、安全校核与措施,以及实际爆破效果。并对爆破中出现的部分问题进行了分析和探讨,为同类工程提供了可借鉴的经验。
Simultaneous demolition of shaft kiln building and kiln structure at the cement plant of the Angang Group in Dalian City was introduced about its blasting design,safety design and actual effect.In the meantime,some of problems in the process of blasting were analyzed and discussed in detail,which provided some referential experiences for similar projects.

关键词(KeyWords): 立窑楼;窑体;爆破拆除;安全防护
Shaft kiln building;Kiln structure;Blasting demolition;Safety protection

Abstract:

Keywords:

基金项目(Foundation):

作者(Author): 付武,王健,付博,马玉罄,毛广田
FU Wu1,WANG Jian1,FU Bo1,MA Yu-qing2,MAO Guang-tian3(1.65066 Troops

扩展功能
本文信息
服务与反馈
本文关键词相关文章
本文作者相关文章
中国知网
分享