三峡三期下游围堰爆破拆除起爆网路设计与可靠性分析
DESIGN AND RELIABILITY ANALYSIS OF INITIATING NETWORK FOR BLASTING DEMOTION OF THE 3RD STAGE DOWNSTREAM COFFERDAM OF THREE GORGES

江小波;饶辉灿;向华仙;张艳;
JIANG Xiao-bo,RAO Hui-can,XIANG Hua-xian,ZHANG Yan (Chongqing Gezhouba Explosive Co.Ltd.,Chongqing 400023,China)

摘要(Abstract):

三峡三期下游围堰爆破拆除网路运用了非电复式交叉接力起爆网路。本文介绍了该工程起爆网路的设计,定量分析了单起爆点起爆同双起爆点起爆及单式加强网路、复式加强网路同复式交叉网路起爆可靠度差异,并建立了数学计算模型,供同类工程借鉴。
The non-electric double crossover relaying initiating network has been used in blasting demolition of the 3rd stage downstream cofferdam of Three Gorges.In the paper,the design of the initiating network for the engineering was introduced.This was followed by comparison of the reliability of different initiating networks,including single initiating spot and double initiating spots,single fortified initiating network,double fortified initiating network and double crossover initiating network.And the mathematic calculating models of these initiating networks were founded.These can be used as a reference for similar projects.

关键词(KeyWords): 三峡工程;围堰;爆破拆除;起爆网路;可靠度
Three Gorges Engineering;Cofferdam;Blasting demolition;Initiating network;Reliability

Abstract:

Keywords:

基金项目(Foundation):

作者(Authors): 江小波;饶辉灿;向华仙;张艳;
JIANG Xiao-bo,RAO Hui-can,XIANG Hua-xian,ZHANG Yan (Chongqing Gezhouba Explosive Co.Ltd.,Chongqing 400023,China)

扩展功能
本文信息
服务与反馈
本文关键词相关文章
本文作者相关文章
中国知网
分享