小间距隧道钻爆施工开挖工序研究The research of the process of drilling and blasting of small spacing tunnel
吴进科;孔恒;傅洪贤;刘琨;刘同良;刘羽;
WU Jin-ke;KONG Heng;FU Hong-xian;LIU Kun;LIU Tong-liang;LIU Yu;Beijing No.1 Municipal Construction Engineering Co.,Ltd.;Beijing Municipal ConstructionCo.,Ltd.;School of Civil Engineering,Beijing Jiaotong University;Beijing No.2 Municipal Construction Engineering Co.,Ltd.;
摘要(Abstract):
采用钻爆法修建小间距隧道时,后行隧道爆破施工将对先行隧道结构产生振动,影响先行隧道的安全性。以北京怀柔区头道穴小间距隧道为工程背景,采用ANSYS软件建立二维数值计算模型,并结合现场监测数据完善计算模型,研究了4种不同施工工序时后行隧道对先行隧道结构产生的振动影响,得出先行隧道迎爆侧边墙受到的振动最大,拱脚处和轮廓线不连续处出现应力集中;因此规定施工中最大段药量不能超过32kg,且先行隧道的下台阶开挖掌子面不宜超越后行隧道上台阶掌子面。若有进度要求,先行隧道宜先开挖左下台阶,以达到保护先行隧道安全的目的。
When small spacing tunnel is built using drilling and blasting,blasting vibration from next built tunnel affects the safety of first built tunnel.Based on Toudaoxue small spacing tunnel in Huairou district of Beijing,the finite element model of actual engineering is modeled by ANSYS software.The finite element model is updated by the monitoring data.According to the finite element model,blasting vibration of first built tunnel is analyzed when four different excavation procedures.It is concluded that the vibration of the side wall of the first built tunnel is the largest,the stress concentration occurs at the foot of the tunnel and the discontinuity of the contour line.It is advised that the maximum charge per delay is less than 32 kg and the face of lower bench of preceding tunnel should not be beyond the tunnel face of backward tunnel.The part of the lower left bench can be excavated in order to reduce the time limit for the tunnel.
关键词(KeyWords):
小间距隧道;爆破施工;动力响应;开挖工序
small spacing tunnel;blasting excavation;dynamic response;the process of excavation
基金项目(Foundation): 国家自然科学基金资助项目(51278042)
作者(Authors):
吴进科;孔恒;傅洪贤;刘琨;刘同良;刘羽;
WU Jin-ke;KONG Heng;FU Hong-xian;LIU Kun;LIU Tong-liang;LIU Yu;Beijing No.1 Municipal Construction Engineering Co.,Ltd.;Beijing Municipal ConstructionCo.,Ltd.;School of Civil Engineering,Beijing Jiaotong University;Beijing No.2 Municipal Construction Engineering Co.,Ltd.;
参考文献(References):
- [1]YANG G L,ROCQUE P,BAWDEN W F,et al.Measurement and analjsis of near-field blast vibration and damage[J].Geotechnical and Geological Engineering,1994,12(2):169-182.
- [2]RAMULU M,CHAKRABORTY A K,SITHARAM T G.Damage assessment of basaltic rock mass due to repeated blasting ina railway tunneling project-A case study[J].Tunnelling and Underground Space Technology,2009,24:208-221.
- [3]傅洪贤,赵勇,谢晋水,等.隧道爆破近区爆破振动测试研究[J].岩石力学与工程学报,2011,30(2):335-340.FU H X,ZHAO Y,XIE J S,et al.Study of blasting vibration test of area near tunnel blasting source[J].Chinese Journal of Rock Mechanics and Engineering,2011,30(2):335-340.
- [4]张庆松,李利平,李术才,等.小间距隧道爆破动力特性试验研究[J].岩土力学,2008,29(10):2 655-2 660,2 666.ZHANG Q S,LI L P,LI S C,et al.Experimental study of blasting dynamic vibration of closely adjacent tunnels[J].Rock and Soil Mechanics,2008,29(10):2 655-2 660,2 666.
- [5]吴亮,卢文波,章克凌,等.侵彻爆炸荷载作用下坑道衬砌破坏机理及影响因素分析[J].岩石力学与工程学报,2005,24(S1):4 900-4 904.WU L,LU W B,ZHANG K L,et al.Analsis of affecting factors and failure mechanism of concrete ling under explosion loading[J].Chinese Journal of Rock Mechanics and Engineering,2005,24(S1):4 900-4 904.
- [6]钟冬望,!秀岩,吴亮,等.上下交叉隧道掘进爆破对既有隧道的动力响应研究[J].武汉科技大学学报,2009,32(1):106-109.ZHONG D W,GAO X Y,WU L.Dynamic response of high and low cross tunneling blasting to the existing adjacent tunnel[J].Journal of Wuhan University of Science and Technology,2009,32(1):106-109.
- [7]刘慧.近距侧爆情况下马蹄形隧道动态响应特点的研究[J].爆炸与冲击,2000,20(2):175-181.LIU H.Dynamic responses of hoof-shaped tunnels to adjacent blastings[J].Explosion and Shock Waves,2000,20(2):175-181.
- [8]卢文波,李海波,陈明.水电工程爆破振动判据及应用中的几个关键问题[J].岩石力学与工程学报,2009,28(8):1 513-1 520.LU W B,LI H B,CHEN M.Safety criteria of blasting vibration in hydropower engineering and several key problems in their application[J].Chinese Journal of Rock Mechanics and Engineering,2009,28(8):1 513-1 520.
- [9]国家安全生产监督管理总局,爆破安全规程:GB 6722-2014[S].北京:中国标准出版社,2015.State Administration of Work Safety.Safety regulations for blasting:GB 6722-2014[S].Beijing:Standards Press of China,2015.
- [10]史雅语,刘慧.招宝山超小间距隧道开挖爆破技术[J].工程爆破,1997,3(4):31-36.SHI Y Y,LIU H.The monitoring of controlled blasting for twin-tunnel with a ultra short net interval in Zhaobao mountain[J].Engineering Blasting,1997,3(4):31-36.
- [11]郗庆桃.隧道爆破振动控制技术[J].爆破,1998,15(4):83-87.XI Q T.Control measures for explosive vibration in tunnel[J].Blasting,1998,15(4):83-87.
- [12]傅洪贤.长距离小间距隧道爆破开挖设计与施工[J].工程爆破,2006,12(3):30-32,39.FU H X.Blasting design and construction of long distance with small clear space tunnel[J].Engineering Blasting,2006,12(3):30-32,39.
- [13]赵高启.新大成二线隧道爆破掘进安全快速施工技术[J].工程爆破,2008,14(1):28-31.ZHAO G Q.Quick and safety construction technology of blast driving of Xindacheng binary line's tunnel[J].Engineering Blasting,2008,14(1):28-31.
- [14]李宁,顾强康,张承客.相邻洞室爆破施工对已有洞室的影响[J].岩石力学与工程学报,2009,28(1):30-38.LI N,GU Q K,ZHANG C K.Influence of blasting on excavation of a new tunnel adjacent to existing tunnel[J].Chinese Journal of Rock Mechanics and Engineering,2009,28(1):30-38.
- [15]朱正国,孙明路,朱永全.超小净距隧道爆破振动现场监测及动力响应分析研究[J].岩土力学,2012,33(12):3 747-3 759.ZHU Z G,SUN M L,ZHU Y Q.Field monitoring on blasting vibration and dynamic response of ultra-small spacing tunnels[J].Rock and Soil Mechanics,2012,33(12):3 747-3 759.
- [16]姚勇,何川.并设小净距隧道爆破振动响应分析及控爆措施研究[J].岩土力学,2009,30(9):2 815-2 822.YAO Y,HE C.Analysis of blasting vibration response of parallel set small clear-distance tunnels and blasting control measures[J].Rock and Soil Mechanics,2009,30(9):2 815-2 822.
- [17]费鸿禄,孙连成,范国利.小净距隧道岩石爆破震动规律研究[J].世界科技研究与发展,2012,34(6):954-957.FEI H L,SUN L C,FAN G L.Reseaches on small inteval tunnel of rock of blasting vibaration law[J].World Sci-Tech R&D,2012,34(6):954-957.
- [18]中国人民共和国交通部.公路隧道设计规范:JTG D70-2004[S].北京:人民交通出版社,2004.Ministry of Communications of the People's Republic of China.Code for design of road tunnel:JTG D70-2004[S].Beijing:China Communications Press,2004.
- [19]HSIN Y L,HONG H.Reliability analysis of reinforced concrete slabs under explosive loading[J].Structural Safety,2001,23:157-178.
- [20]汪波,何川,夏炜洋.爆破施工新建地铁隧道与既有运营地铁的相互动力响应研究[J].中国铁道科学,2001,32(5):64-70.WANG B,HE C,XIA W Y.Study on interactive dynamic resonses between the new-built subway tunnel by blasting construction and the exiting operation subway tunnel[J].China Railway Science,2001,32(5):64-70.
- [21]王继槐,刘辉,颜东煌.小间距隧道爆破振动影响分析[J].中外公路,2012,32(3):268-271.WANG J H,LIU H,YAN D H.Analysis of blasting vibration of small spacing tunnel[J].Journal of China&Foreign Highway,2012,32(3):268-271.
- [22]李云鹏,艾传志,韩常领.小间距隧道爆破开挖动力效用数值模拟研究[J].爆炸与冲击,2007,27(1):74-80.LI Y P,AI C Z,HAN C L.Study on dynamics effect caused by blasting construction by numerical simulation for tunnels with small spacing[J].Explosion and Shock Waves,2007,27(1):74-80.
- 吴进科
- 孔恒
- 傅洪贤
- 刘琨
- 刘同良
- 刘羽
WU Jin-ke- KONG Heng
- FU Hong-xian
- LIU Kun
- LIU Tong-liang
- LIU Yu
- Beijing No.1 Municipal Construction Engineering Co.
- Ltd.
- Beijing Municipal ConstructionCo.
- Ltd.
- School of Civil Engineering
- Beijing Jiaotong University
- Beijing No.2 Municipal Construction Engineering Co.
- Ltd.
- 吴进科
- 孔恒
- 傅洪贤
- 刘琨
- 刘同良
- 刘羽
WU Jin-ke- KONG Heng
- FU Hong-xian
- LIU Kun
- LIU Tong-liang
- LIU Yu
- Beijing No.1 Municipal Construction Engineering Co.
- Ltd.
- Beijing Municipal ConstructionCo.
- Ltd.
- School of Civil Engineering
- Beijing Jiaotong University
- Beijing No.2 Municipal Construction Engineering Co.
- Ltd.