突变截面高烟囱分段爆破拆除及振动控制Segmented blasting demolition and vibration control of a high chimney with sudden changed sections
曹娟;申雷;盖四海;张英才;
CAO Juan;SHEN Lei;GAI Si-hai;ZHANG Ying-cai;Henan Xunda Blasting Co.,Ltd.;Jiaozuo Radio,Film & Television Bureau;College of Civil Engineering,Henan Polytechnic University;
摘要(Abstract):
为了达到安全拆除180m钢筋混凝土烟囱的目的,根据烟囱截面尺寸变化差异大、周围环境复杂和倒塌空间不足的特点,结合复杂环境下突变截面高烟囱分段爆破拆除工程实例,采用两次高位切口单向控制爆破拆除技术,上部切口采用倒梯形爆破切口,下部切口采用正梯形爆破切口。通过精心设计、施工,实现了烟囱准确定向并有效控制了烟囱的后坐。根据理论计算公式校核了爆破振动和塌落触地振动速度以及爆破飞石距离。采取铺设缓冲垫层、开挖减振沟等措施减小振动,并通过分析爆破振动监测数据,证实了这些措施对振动控制的有效性和实用性,可为同类工程提供参考。
In order to achieve the purpose of blasting demolition a 180 mhigh reinforced concrete chimney safely,according to the characteristics of differences of the chimney section size changes,complex surrounding environment and the insufficient collapse space,combined with the engineering example of segmented blasting demolition of high chimney with sudden changed sections,high location notch unidirectional control blasting demolition technique was used twice,upper notch was inverted trapezoid and lower notch was trapezoid.Through careful design and construction,accurate orientation was achieved and the backward collapse of the chimney was controlled effectively.Blasting vibration velocity,collapsing touchdown vibration velocity and the distance of blasting flying rocks were checked by theoretical calculation formula.Some measures such as laying a cushion,excavating damping ditch were taken to reduce vibration.By analyzing the blasting vibration monitoring data,the effectiveness and practicability of the above vibration control measures were proved.It could provide a reference for similar projects.
关键词(KeyWords):
突变截面;高位切口烟囱;分段爆破拆除;防护措施;振动控制
sudden changed sections;high notch chimney;segmented blasting demolition;protective measures;vibration control
基金项目(Foundation): 国家自然科学基金资助项目(51504082)
作者(Authors):
曹娟;申雷;盖四海;张英才;
CAO Juan;SHEN Lei;GAI Si-hai;ZHANG Ying-cai;Henan Xunda Blasting Co.,Ltd.;Jiaozuo Radio,Film & Television Bureau;College of Civil Engineering,Henan Polytechnic University;
参考文献(References):
- [1]王小波,李长山,谢国森,等.十层框架结构楼房的单向折叠爆破拆除[J].爆破,2006,23(4):42-45.WANG X B,LI C S,XIE G S,et al.Undirectional fold blasting demolition of a ten-storey frame construction building[J].Blasting,2006,23(4):42-45.
- [2]张英才,张海涛,董保立,等.复杂环境下150m砼烟囱两段单向控制爆破技术[J].工程爆破,2014,20(6):16-20.ZHANG Y C,ZHANG H T,DONG B L,et al.The unidirectional controlled blasting technology under complicated environment in two sections of a 150 m reinforced concrete chimney[J].Engineering Blasting,2014,20(6):16-20.
- [3]褚怀保,乔俊凤,张英,等.180m高钢筋混凝土烟囱三段单向控制爆破拆除[J].工程爆破,2010,16(4):61-63.CHU H B,QIAO J F,ZHANG Y,et al.Demolition of a 180mhigh reinforced concrete chimney by three sections one-way controlled blasting[J].Engineering Blasting,2010,16(4):61-63.
- [4]周家汉.爆破拆除塌落振动速度计算公式的讨论[J].工程爆破,2009,15(1):1-4.ZHOU J H.Discussion calculation formula of collapsing vibration velocity caused by blasting demoliton[J].Engineering Blasting,2009,15(1):1-4.
- [5]郑炳旭.中国爆破新技术Ⅲ[M].北京:冶金工业出版社,2012:659-681.ZHENG B X.New blasting technology in ChinaⅢ[M].Beijing:Metallurgical Industry Press,2012:659-681.
- 突变截面
- 高位切口烟囱
- 分段爆破拆除
- 防护措施
- 振动控制
sudden changed sections - high notch chimney
- segmented blasting demolition
- protective measures
- vibration control
- 曹娟
- 申雷
- 盖四海
- 张英才
CAO Juan- SHEN Lei
- GAI Si-hai
- ZHANG Ying-cai
- Henan Xunda Blasting Co.
- Ltd.
- Jiaozuo Radio
- Film & Television Bureau
- College of Civil Engineering
- Henan Polytechnic University
- 曹娟
- 申雷
- 盖四海
- 张英才
CAO Juan- SHEN Lei
- GAI Si-hai
- ZHANG Ying-cai
- Henan Xunda Blasting Co.
- Ltd.
- Jiaozuo Radio
- Film & Television Bureau
- College of Civil Engineering
- Henan Polytechnic University