45m钢筋混凝土烟囱同向折叠爆破拆除
Demolition of 45m reinforced concrete chimney with co-rotating folded blasting

邹宗山;杨军;李福强;佐建君;杨忠豪;
ZOU Zong-shan;YANG Jun;LI Fu-qiang;ZUO Jian-jun;YANG Zhong-hao;State Key Laboratory of Explosion Science and Technology,School of Mechatronical Engineering,Beijing Institute of Technology;Beijing BIT Blasting Engineering & Technology Co.,Ltd.;

摘要(Abstract):

为了安全实施45m钢筋混凝土烟囱在距33m处高压线和倒塌空间受限环境中的爆破拆除,采取双切口同向折叠爆破拆除技术,最终确定上、下切口延时时间5s,超长的延时时间保证了烟囱上段筒体倾倒加速后下段筒体才开始倾倒,避免烟囱上段筒体倒塌发生前倾现象,缩短了烟囱的倒塌长度,使其在32m以内,确保了高压线的安全。该工程对于烟囱双切口同向折叠及延时时间的选择具有一定的借鉴意义。
The distance was only 33 mbetween the 45 mhigh reinforced concrete chimney and the high voltage line.The collapse space was limited for the chimney collapsing.In order to ensure the safety of the high voltage lines,the co-rotating folded blasting demolition technique was used.Moreover,the delay interval was 5sbetween the upper and lower blasting notch initiated.Overlong delay interval ensured the lower chimney start to collapsing after the upper chimney dumping acceleration,avoided the forward rush of the upper chimney section,and shortened the collapse length of the chimney within 32 m.The project had a certain significance to select the delay interval with the co-rotating folded blasting demolition.

关键词(KeyWords): 钢筋混凝土;烟囱;折叠爆破;爆破参数;延时时间
Reinforced concrete;Chimney;Folded blasting;Blasting parameters;Delay interval

Abstract:

Keywords:

基金项目(Foundation):

作者(Authors): 邹宗山;杨军;李福强;佐建君;杨忠豪;
ZOU Zong-shan;YANG Jun;LI Fu-qiang;ZUO Jian-jun;YANG Zhong-hao;State Key Laboratory of Explosion Science and Technology,School of Mechatronical Engineering,Beijing Institute of Technology;Beijing BIT Blasting Engineering & Technology Co.,Ltd.;

参考文献(References):

扩展功能
本文信息
服务与反馈
本文关键词相关文章
本文作者相关文章
中国知网
分享