14层办公楼定向爆破拆除DIRECTIONAL BLASTING DEMOLITION OF 14-STOREY OFFICE BUILDING
康翠平;高艳敏;孙江;王海峰;
KANG Cui-ping GAO Yan-min SUN Jiang WANG Hai-feng (China Railway No.9 Bureau Group Blasting Engineering Co.,Ltd.,Shenyang 110002,China)
摘要(Abstract):
待爆破拆除的14层办公楼为框架结构,南北长29m、东西宽19m,最高处为46.2m,总建筑面积6000m2。施工过程中采用支撑轴前移的方法,有效地控制了楼体后坐。由于设计了合理的爆破参数,采取了有效的安全防护措施,使爆破拆除达到了预期效果。
Towering 46.2 m at its highest point and covering a construction area of 6000 square meters, the building to be demolished was a 14-storey office building in frame structure with a length of 29 m from north to south and a width of 19 m from east and west.Backlashing phenomenon was effectively controlled by using the method of forwarding back shaft in blasting operation.Thanking to the reasonable blasting parameters cooperated with the safety protection measures,the demolition saw an ideal blasting effect.
关键词(KeyWords):
框架结构;定向爆破;后坐;支撑轴前移;安全防护
Frame structure;Directional blasting;Backlashing phenomenon;Back shaft-forwarding;Safety protection
基金项目(Foundation):
作者(Authors):
康翠平;高艳敏;孙江;王海峰;
KANG Cui-ping GAO Yan-min SUN Jiang WANG Hai-feng (China Railway No.9 Bureau Group Blasting Engineering Co.,Ltd.,Shenyang 110002,China)
参考文献(References):
- [1]刘殿中.工程爆破实用手册[M].北京:冶金工业出版社,1999.
- [2]齐世福,胡良孝,李尚海.17层综合办公楼定向爆破拆除[J].工程爆破,2003,9(3):29-33.
- [3]付武,王永强,蒋金玉,郭福德.120m高钢筋混凝土烟囱爆破拆除[J].工程爆破,2006,12(4):35-37.
- [4]中国铁道工程学会爆破专业委员会.铁道工程爆破文集[M].北京:中国铁道出版社,2000.
- [5]冯叔瑜,吕毅,杨杰昌,顾毅成.城市控制爆破[M].北京:中国铁道出版社,1985.
- [6]孙江,王海峰,蔡伟,等.46700m~2楼房一次爆破拆除[J].工程爆破,2008,14(2):45-47.
- 框架结构
- 定向爆破
- 后坐
- 支撑轴前移
- 安全防护
Frame structure - Directional blasting
- Backlashing phenomenon
- Back shaft-forwarding
- Safety protection
- 康翠平
- 高艳敏
- 孙江
- 王海峰
KANG Cui-ping GAO Yan-min SUN Jiang WANG Hai-feng (China Railway No.9 Bureau Group Blasting Engineering Co.- Ltd.
- Shenyang 110002
- China)
- 康翠平
- 高艳敏
- 孙江
- 王海峰
KANG Cui-ping GAO Yan-min SUN Jiang WANG Hai-feng (China Railway No.9 Bureau Group Blasting Engineering Co.- Ltd.
- Shenyang 110002
- China)