关于非电毫秒雷管名义延期时间的讨论DISCUSSION ON NOMINAL DELAY INTERVALS OF NONELECTRIC MILLISECOND DETONATORS
杨享衢
YANG Xiang-qu (The third General Corps,Hydroelectric Armed Police,Chengdu 610036, China)
摘要(Abstract):
从微差间隔时间、微差起爆网路等方面分析了设置非电毫秒雷管名义延期时间应当考虑的因素 ,指出了目前生产的非电毫秒雷管在使用中所遇到的实际问题 ,并提出了对现行非电毫秒雷管名义延期时间的修改建议
From respects of delay time and priming circuit for millisecond blasting,the factors that should be considered when setting the nominal delay intervals of nonelectric millisecond detonators are studied The practical problems met in application of existing nonelectric millisecond detonators are pointed out Some proposals for resetting the nominal delay intervals of nonelectric millisecond detonators are put forward
关键词(KeyWords):
微差爆破;非电雷管;延期时间;起爆网路;爆破安全
Millisecond blasting;Nonelectric detonator;Delay interval;Priming circuit; Blasting safety
基金项目(Foundation):
作者(Author):
杨享衢
YANG Xiang-qu (The third General Corps,Hydroelectric Armed Police,Chengdu 610036, China)
- 微差爆破
- 非电雷管
- 延期时间
- 起爆网路
- 爆破安全
Millisecond blasting - Nonelectric detonator
- Delay interval
- Priming circuit
- Blasting safety