工程爆破

2021, v.27(05) 47-52

[打印本页] [关闭]
本期目录(Current Issue) | 过刊浏览(Past Issue) | 高级检索(Advanced Search)

基于TBM法的地铁大断面水压爆破技术
Water pressure blasting technology for a merto large cross section based on the TBM method

王新明;
WANG Xin-ming;China Railway Eleventh Bureau Group Co., Ltd.;

摘要(Abstract):

为了顺利完成地铁区间四线大断面爆破开挖,减小爆破作业对城市环境的影响,利用TBM导洞扩挖形成既有临空面,采用水压爆破施工技术,通过质点振速的理论计算与现场起爆试验结果,优化了爆破参数和起爆网路,进而降低了质点爆破振速,完成了区间大断面开挖,减小了爆破对周边环境的影响。结果表明:相比于常规爆破技术,本工程的水压爆破方案每循环节省了炸药39.91 kg,每循环进尺提高了0.35 m,大块率降低了53%,质点爆破振速下降了0.13 cm/s,粉尘浓度下降了36.6 mg/m3,经济与环境效益显著。
In order to successfully complete the large section blasting excavation of a 4-line metro section and reduce the impact of blasting operation on the urban environment, the TBM pilot tunnel was expanded to form the existing free face. The hydraulic blasting construction technology is applied. Through theoretical calculation of particle vibration velocity and field initiation test results, the blasting parameters and initiation network are optimized to reduce the particle blasting vibration velocity. The large section excavation is completed, and the blasting impact on the surrounding environment is reduced. The results show that compared with conventional blasting technology, the hydraulic blasting scheme of this project saves 39.91 kg of explosives per cycle, increases the footage by 0.35 m per cycle, reduces the bulk rate by 53 %, and decreased the particle blasting vibration velocity by 0.13 cm/s and the dust concentration by 36.6 mg/m3,经济与环境效益显著。
In order to successfully complete the large section blasting excavation of a 4-line metro section and reduce the impact of blasting operation on the urban environment, the TBM pilot tunnel was expanded to form the existing free face. The hydraulic blasting construction technology is applied. Through theoretical calculation of particle vibration velocity and field initiation test results, the blasting parameters and initiation network are optimized to reduce the particle blasting vibration velocity. The large section excavation is completed, and the blasting impact on the surrounding environment is reduced. The results show that compared with conventional blasting technology, the hydraulic blasting scheme of this project saves 39.91 kg of explosives per cycle, increases the footage by 0.35 m per cycle, reduces the bulk rate by 53 %, and decreased the particle blasting vibration velocity by 0.13 cm/s and the dust concentration by 36.6 mg/m3, which reveals that the significant economic and environmental benefits of this technology.

关键词(KeyWords): 水压爆破;TBM法;临空面;起爆网路;爆破振速;大断面
water pressure blasting;TBM method;free face;initiation network;blasting vibration velocity;large cross section

Abstract:

Keywords:

基金项目(Foundation): 国家重点研发计划资助项目(2017YFB1302600)

作者(Authors): 王新明;
WANG Xin-ming;China Railway Eleventh Bureau Group Co., Ltd.;

DOI: 10.19931/j.EB.20200089

参考文献(References):

扩展功能
本文信息
服务与反馈
本文关键词相关文章
本文作者相关文章
中国知网
分享